Uzbekistan · south of Tashkent · about four years of work

Central Asia Smart City

South of Tashkent, between New Tashkent and Ohangaron, we designed a 6,400-hectare smart city with an international free economic zone, logistics hub and financial centre. The project was developed over about four years. It aims to take traffic and industrial pressure off the capital, raise production and export capacity in line with the Uzbekistan 2030 strategy, and create a centre that supports New Tashkent.

Central Asia Smart City kuşbakışı görselleştirme
6.400ha planning area
300.000residents in the smart city
501.000jobs (150,000 in industry)
18–24USD bn total investment
9–13USD bn annual value added

Location

The site sits on the Tashkent–Ohangaron A373 highway and the railway line, at the head of the corridor to Ohangaron and the Fergana Valley.

DestinationDistance
Tashkent city centre34 km
Tashkent International Airport30 km
New Tashkent International Airport15 km
Tashkent boundary / New Tashkent10 km
Olmaliq10 km
Ohangaron8 km
Nurafshon7 km

Why here?

Relieving the capital

Alternative transport and energy infrastructure for industry and logistics to ease traffic and environmental pressure on central Tashkent.

Balanced growth through sub-centres

Redistributing population and activity for productive, sustainable growth across the region.

Proximity and access

Close to a capital with a ready market, a trained workforce and strong infrastructure.

Long-term vision

Optimised transport, diversified energy and sustainable standards to strengthen Tashkent's competitiveness and reach in Central Asia.

Master plan: 6,400 ha land use

Useha%
Urban green space1.57524,6
International free economic trade and industry zone1.45522,7
Financial centre and smart city1.14417,9
Roads, parking and squares94614,8
International logistics centre73011,4
Social and technical infrastructure5518,6
Total6.400100,0

First operations in 3 years and completion in 12–15 years. Expected results: 7,500–10,600 businesses, USD 2.5–3 bn of exports and USD 2–2.5 bn of tax revenue a year. Growth follows an eight-stage plan that manages financial sustainability, market dynamics, technological adaptation and operational efficiency together.

Phase 1: 530 ha

ZoneSub-useha
IndustrySmall (up to 1,500 m²) 46 · medium (1,501–5,000 m²) 164 · large (over 5,000 m²) 130340
Commercial & administrative centreTrade centre 61 · administrative and social facilities 59120
LogisticsCovered storage 17 · open storage 12 · support units 635
HousingHousing 25 · facilities 10; 1,900 homes, 8,290 residents35
Total530

Phase 1 targets: USD 1.2–1.5 bn of investment, 3,500–4,000 businesses, USD 350–400 m of annual value added, and 21,400 industrial and 11,100 service jobs. First operations in 1–2 years, completion in 6–8 years.